The timeline is as follows:
- Monday 12th September = Project Start Date
- Monday 12th September-Thursday October 6th = Planning and Reasearch For The Project
- Friday 7th October-Friday 21st October = Filming and Editing of Video Project
- Friday 21st October = Deadline For First Draft Of Film Project
- Monday 24th October-Friday 28th October = Half Term (Use Time to Plan Print Project)
- Monday 31st October-Friday 4th November = Planning of print task
- Monday 7th November-Friday 11th November = Making changes to video task
- Monday 14th Novmeber-Thursday 1st December = Development and Completion of Print Project
- Thursday 1st December-Thursday 8th December = Evaluation of the overall task
- Thursday 8th December = FINAL DEADLINE!!